Works in the Department of Biology are progressing well and are on schedule. So far, almost all the electrical, plumbing and fire alarm infrastructure has been completed and most of the plastering in all rooms has been done. Currently, electrical wiring and cabling works are taking place, finalising of the AC piping and ventilation works within the rooms and penetration works for external infrastructure are taking place. Tiling works have also started in some areas.
One hopes that the mechanical and electrical works will be finalised by the beginning of the forthcoming academic year. Meanwhile, the tender for office furniture has been issued and is being adjudicated whereas submission of bids for adjudication for the lab furniture tender is due in the coming days. The AV tender should also be issued in the coming weeks.